PROJECT:
WATER TREATMENT PLANT
LOCATION
Warkworth
CLIENT
Water
SETTING THE SCENE
Demand for water is increasing as our population grows. We work with water services providers and industry suppliers to offer innovative engineering and cost-saving solutions across any project so we can all enjoy a safe, clean environment.
We deliver projects from start-up to completion. For our clients, this means a single point of contact for installing water and wastewater pipes of all sizes and types within an agreed programme.
SOLUTION
The distance involved was 1.5 km. Requiring the installation of 90 mm Wastewater Rising Main for 0.55 km; 50 mm Wastewater Rising Main for 0.55 km and a 355 mm Watermain for 0.35 km.
In the process a cost saving to the client was identified by putting 90 mm and 50 mm pipes into a single bore. The fact the project was delivered on time and met all technical specifications made the ‘taste’ even sweeter.
Download
Project Sheet